Traffic Advisory: Sanitary Sewer Main Install at Cuaulta Crescent

Type(s)
Public Notice
Image
Banner apologizing for traffic delays due to improvements in Colwood.

Traffic delays are expected:

When:   February 21, 2024, to March 29, 2024 – 7:00am to 5:00pm
Where:  Cuaulta Crescent near Sewell Road ​​​​​​​
What:    Sanitary Sewer Main installation

You may need to wait a few minutes when leaving or arriving in the neighborhood near Cuaulta Crescent and Sewell Road.

The developer will be installing a Sanitary Sewer main on Cuaulta Crescent, beginning at Sewell Road and progressing up to 783 Cuaulta Crescent.

During the hours of 7:00am to 5:00pm, single lane alternating traffic will be in effect along this route to facilitate the sewer main installation. While some minor delays may occur, efforts will be made to minimize impacts on travel times. Please plan your commute accordingly.

Emergency vehicle access will be maintained at all times.

Traffic personnel will be onsite only during the hours of 7am to 5pm to direct traffic. Please follow their directions, obey traffic signs, and use caution after hours.

Work Area:

Image
Map highlighting the work zone for sanitary sewer main installation on Cualta Crescent at Sewell Road, scheduled from February 21 to March 29, 2024.

Contact for the works:  

Andrew Robertson
Akin Construction​​​​​​​
250-778-584-3436 or akinrobertson7@gmail.com 

Get details and check traffic maps at www.colwood.ca/Roads